英语翻译
4.1 甲方要求比合同约定的工期提前竣工时,应征得乙方同意,并支付乙方因赶工采取的措施费用.
4.2 因甲方未按约定完成工作,影响工期,工期顺延.
4.3 因乙方责任,不能按期开工或中途无故停工,影响工期,工期不顺延,并赔偿甲方相应损失.
4.4 因设计变更或非乙方原因造成的停电、停水、停气及不可抗力因素影响,导致停工8小时以上,工期相应顺延.
▼优质解答
答案和解析
4.1 Party demanding than the contract completion ahead of schedule, shall obtain the consent of Party B and Party B to pay the costs of measures taken to rush.
 
4.2 Party A fails to agree due to complete its work, the impact duration, extension of time.
 
4.3 Party B liability can not be scheduled to start or halfway undue downtime, affect the duration, the duration is not extended, and compensation for consequential loss Party.
 
4.4 due to design changes or B causes power outages, water, gas stop and force majeure factors, led to more than 8 hours downtime, time shall be extended accordingly.
看了 英语翻译4.1甲方要求比合同...的网友还看了以下:

电容器是一种重要的电学元件,基本工作方式就是充电和放电.由这种充放电的工作方式延伸出来的许多电学现  2020-07-22 …

延长线段AB是指按端点A到B的方向延长;延长线段BA是指按从端点B到A的方向延长,这时也可以说反向  2020-07-30 …

英语翻译4.1甲方要求比合同约定的工期提前竣工时,应征得乙方同意,并支付乙方因赶工采取的措施费用.  2020-07-30 …

求土方工程量计算基坑顶面尺寸50*38.5m2,平均放坡1m,平均挖深5.7m,扣减东北角(三角形)  2020-11-07 …

被誉为全国爱国主义教育示范基地“一号工程”的延安革命纪念馆正式对外开放,这对继承和发扬伟大的延安精神  2020-11-13 …

被誉为全国爱国主义教育示范基地“一号工程”的延安革命纪念馆正式对外开放,这对继承和发扬伟大的延安精神  2020-12-18 …

下列各句中,加点的成语使用恰当的一项是(3分)A.上海在延迟退休方面率先试点,进行城镇企业职工“柔性  2021-01-02 …

某项工程,有三种施工方案:1、甲队单独施工,能按期完成;2、乙队单独施工,需延期五天完成;3、两队联  2021-01-02 …

某项工程,有三种施工方案:1、甲队单独施工,能按期完成;2、乙队单独施工,需延期五天完成;3、两队联  2021-01-02 …

某项工程有三种施工方案由甲队单独施工,能按工期完成某项工程,有三种施工方案:①甲队单独施工,能按期完  2021-01-02 …