The( )provides the project manager with the authority to apply organizational resources t

题目

The( )provides the project manager with the authority to apply organizational resources to project activities。

A.project management plan

B.project charter

C.project human resource plan

D.project stakeholders

参考答案
正确答案:B
项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。
看了The( )provides ...的网友还看了以下:

People gave away a large number of money.with pro 英语 2020-05-16 …

● The project life-cycle can be described as(72). 计算机类考试 2020-05-25 …

● Risk management allows the project manager and t 计算机类考试 2020-05-25 …

●To ensure the project team provides the functiona 计算机类考试 2020-05-26 …

The key benefit of ( )is that it provides guidance 计算机类考试 2020-05-26 …

The( )provides the project manager with the author 计算机类考试 2020-05-26 …

The( )provides the project manager with the author 计算机类考试 2020-05-26 …

Project Quality Management must address the manage 计算机类考试 2020-05-26 …

The (73) provides the project manager with the aut 计算机类考试 2020-05-26 …

The( )is a hierarchical decomposition of the total 计算机类考试 2020-05-26 …