● (73) is one of the techniques used for estimating activity durations. (73)A.Analogous Es
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
试题(73)分析
下列用于活动历时估算的技术是答案A类比估算法。
参考答案
(73)A
1.It sounds( )a plane is flying overhead A.like B 英语 2020-05-14 …
you'dbetter()back to the office A.go B.to go C.go 英语 2020-05-16 …
She always ________ her family should do everythi 英语 2020-05-16 …
1.It's time___up,or he'll be late for school..A.o 英语 2020-05-17 …
● (73) is a method used in Critical Path Methodolo 计算机类考试 2020-05-25 …
● (73) is one of the techniques used for estimatin 计算机类考试 2020-05-26 …
试题(73)Tool for defining activities is(73).(73)A.De 计算机类考试 2020-05-26 …
●A 10BaseT Ethernet LAN has (73).(73)A. a star top 计算机类考试 2020-05-26 …
●In the following,which is not a method for inter- 计算机类考试 2020-05-26 …
● (73) is a query language for manipulating data i 计算机类考试 2020-05-26 …