● (73) is a method used in Critical Path Methodology for constructing a project schedule n
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM
试题(73)分析
(73) 用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称作节点)代表活动,它们之间用箭头连接,显示彼此之间存在的逻辑关系。
A.PERT B.AOA C.WBS D.PDM
参考答案
(73)D
I'mbusinesshere.ThisVCDisusedbusinessnotplaying.A 英语 2020-04-27 …
英语翻译For this reason it is essential that quotatio 英语 2020-05-13 …
We see things_____our eyes.A by B in C with D for 英语 2020-05-16 …
1.He did not want to go( ).A.for one reason and o 英语 2020-05-16 …
● (73) is a method used in Critical Path Methodolo 计算机类考试 2020-05-25 …
● (73) is a query language for manipulating data i 计算机类考试 2020-05-26 …
编程,从键盘输入1个人的工资(1000—9999之间的整数),计算给这个人发工资时,需面值100元 其他 2020-07-18 …
继续高二英语1,Hewaswanderingthroughthestreet,lookingaro 英语 2020-07-22 …
2、以下关于for语句的说法不正确的是().2、以下关于for语句的说法不正确的是().A.for循 其他 2020-12-15 …
下列for循环语句中不正确的一个是()A.for{;;;}{}B.for(inta=100;true 其他 2020-12-15 …