● You are a project manager for a small project. Your project was budgeted for ¥500,000 ov
● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .
(74)
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
跪求一个首歌是英文,歌词大概是i know i know……everything you do a 其他 2020-05-14 …
Austria—The leading bird in a European project to 英语 2020-05-14 …
do you still have my back like when you was my fr 英语 2020-05-16 …
英语翻译1.The girl was wearing someone else's dress.2 英语 2020-05-16 …
Teacher:You were _____for school yesterday.Peter: 英语 2020-05-16 …
what do you think of the basketball match last ni 英语 2020-05-16 …
-could you tell me () at that time?-I was Watchin 英语 2020-05-16 …
英语翻译Is this Janet,Mum?Yes,she was just two years 英语 2020-05-17 …
● You are a project manager for a small project. Y 计算机类考试 2020-05-26 …
You are a project manager for a small project. You 计算机类考试 2020-05-26 …