______is primarily concerned with defining and controlling what is and is not included in
______is primarily concerned with defining and controlling what is and is not included in the project.
A.Project Time Management
B.Project Cost Management
C.Project Scope management
D.Project Communications Management
解析:项目范围管理是项目管理(包括时间、成本、沟通)的基础。
项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理,因此应选择C。
猜谜语:what is in the middle of the world?teacher wr 英语 2020-05-13 …
Want what you have and care not for what you don" 英语 2020-05-16 …
I love you,not because what you are,just because 英语 2020-05-16 …
读下面一小段文字,选择正确答案In addition to looking acceptable, 英语 2020-05-16 …
英语翻译Have forgotten him,it is not my fault.In the 英语 2020-05-17 …
● (74) is primarily concerned with defining and co 计算机类考试 2020-05-26 …
● ()is primarily concerned with defining and conce 计算机类考试 2020-05-26 …
______is primarily concerned with defining and con 计算机类考试 2020-05-26 …
()is not included in the main contents of the oper 计算机类考试 2020-05-26 …
(75)is primarily concerned with defining and contr 计算机类考试 2020-05-26 …