The( )Process Group consists of the processes used to complete the work defined in the p

题目

The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out

参考答案
正确答案:B
执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。
看了The( )Process G...的网友还看了以下:

英语翻译HRM is the process for creating and maintaini 英语 2020-05-14 …

(c) Discuss the ways in which budgets and the budg 财会类考试 2020-05-21 …

3 Organisations need to recruit new employees. An 财会类考试 2020-05-21 …

● Configuration management is the process of manag 计算机类考试 2020-05-25 …

The( )Process Group consists of the processes used 计算机类考试 2020-05-26 …

● The development process in the software (74) inv 计算机类考试 2020-05-26 …

Configuration management is the process of managin 计算机类考试 2020-05-26 …

When a process is in control, what do you want to 计算机类考试 2020-05-26 …

In project time management, activity definition is 计算机类考试 2020-05-26 …

Host 1 has just started up and requests a web page 计算机类考试 2020-05-31 …