● Project Time Management includes the processes required to manage timely completion of t

题目

● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

(74)

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities

参考答案
正确答案:A
试题(74)分析
    项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
参考答案
    (74)A