Risk management allows the project manager and the project team not to (71).A.eliminate most risks during the planning phase of the projectB.identify
The quality management plan should describe how the project management team will implement its quality(73).A.improvementB.controlC.policyD.informatio
A quality assurance team should be(75)。① associated with any particular development group② depended upon any particular development group③ responsibl
●Adding 5 people to a 4 person team increases the communication channels by a factor of (75).(75) A. 3 timesB. 4 timesC. 5 timesD. 6 times
●The quality management plan should describe how the project management team will implement its quality (73).(73) A. improvementB. controlC. policyD.
SWOT analysis is a kind of risk identification method.If the project team chose me WT strategy, they should( ). A.overcome the weakness and reduce th
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identif
● SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should __(75)__.(75)A.make full use of the a
●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-o
● A quality assurance team should be(75).①associated with any particular development group②depended upon any particular development group③responsible