A project manager believes that modifying the scope of the project may provide added value
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。
4.Many people hold the opinion that May and Octob 英语 2020-05-17 …
英语翻译1.01 The purpose of this Memorandumis to prov 英语 2020-05-17 …
2 (a) Discuss the nature of the financial objectiv 财会类考试 2020-05-21 …
(c) Discuss the difficulties that may be experienc 财会类考试 2020-05-21 …
(d) Explain the term ‘environmental management acc 财会类考试 2020-05-21 …
(c) Discuss the practical problems that may be enc 财会类考试 2020-05-21 …
(iii) Identify and discuss an alternative strategy 财会类考试 2020-05-21 …
(ii) Discuss TWO problems that may be faced in imp 财会类考试 2020-05-21 …
●The TCP protocolis a (71) layer protocol. Each co 计算机类考试 2020-05-26 …
The TCP protocolis a (71) layer protocol. Each con 计算机类考试 2020-05-26 …