搭设尺寸为:立杆的横距为 1.2m,立杆的纵距为1.5m,大小横杆的步距为1.8 m;
内排架距离墙长度为0.15m;
大横杆在上,搭接在小横杆上的大横杆根数为 1 根;
The steel pipe type:Φ 48 x 3.5
横杆与立杆连接方式为单扣件;
1.1搭设方案和程序
落地脚手架搭设顺序如下(工程只能见到7层以下的脚手架搭设和实用)
⑴将地基夯实,按立杆间距放置预制砼垫块.
⑵搭设程序:摆放扫地杆→逐根立立杆与扫地杆扣紧→扫地杆小横杆与立杆及扫地杆扣紧→装第一步大横杆并与立杆扣紧→安装第一步小横杆→安装第二步大横杆→安装第三小横杆→加设临时斜撑杆(上端与第一大横杆扣紧,装设连墙杆后拆)→安装第三、四步大横杆和小横杆→连接墙杆→接立杆→加设剪刀撑→铺脚手片→扎防护栏板挡脚板,并挂设安全网防护.
⑶沿脚手架纵向两端和转角起,在脚手架外侧每隔9 M用斜面杆成剪刀撑,自上而下循序连续设置,斜面杆与地面成45-60度夹角,剪刀撑钢管接长应用搭接方法,搭接长度不小于40CM.
⑷脚手架外侧自第二步起,每步设1.2M高的防护栏杆和30CM高的挡脚板.
⑸搭设时应随搭随校正杆件的垂直和水平偏差,同时适度拧紧扣件,连接大横杆的对接扣件,开口应朝架子内侧,螺栓朝上,防止雨水进入.
⑹各杆件相交伸出的端头均要大于100MM,防止杆件滑脱.
⑺剪刀撑搭设要将一根斜扣在立杆上,另一端扣在小横杆伸出部分上,斜杆两端扣件与立杆的距离不大于200MM.
搭设尺寸为:立杆的横距为 1.2m,立杆的纵距为1.5m,大小横杆的步距为1.8 m;
内排架距离墙长度为0.15m;
大横杆在上,搭接在小横杆上的大横杆根数为 1 根;
The steel pipe type:Φ 48 x 3.5
横杆与立杆连接方式为单扣件;
1.1搭设方案和程序
落地脚手架搭设顺序如下(工程只能见到7层以下的脚手架搭设和实用)
⑴将地基夯实,按立杆间距放置预制砼垫块.
⑵搭设程序:摆放扫地杆→逐根立立杆与扫地杆扣紧→扫地杆小横杆与立杆及扫地杆扣紧→装第一步大横杆并与立杆扣紧→安装第一步小横杆→安装第二步大横杆→安装第三小横杆→加设临时斜撑杆(上端与第一大横杆扣紧,装设连墙杆后拆)→安装第三、四步大横杆和小横杆→连接墙杆→接立杆→加设剪刀撑→铺脚手片→扎防护栏板挡脚板,并挂设安全网防护.
⑶沿脚手架纵向两端和转角起,在脚手架外侧每隔9 M用斜面杆成剪刀撑,自上而下循序连续设置,斜面杆与地面成45-60度夹角,剪刀撑钢管接长应用搭接方法,搭接长度不小于40CM.
⑷脚手架外侧自第二步起,每步设1.2M高的防护栏杆和30CM高的挡脚板.
⑸搭设时应随搭随校正杆件的垂直和水平偏差,同时适度拧紧扣件,连接大横杆的对接扣件,开口应朝架子内侧,螺栓朝上,防止雨水进入.
⑹各杆件相交伸出的端头均要大于100MM,防止杆件滑脱.
⑺剪刀撑搭设要将一根斜扣在立杆上,另一端扣在小横杆伸出部分上,斜杆两端扣件与立杆的距离不大于200MM.
▼优质解答
答案和解析
Erection size:a vertical rod of the horizontal distance 1.2m,a vertical rod longitudinal distance 1.5m,size bar step distance of 1.8 m;
The inner frame distance from the wall length 0.15m;
A large bar on lap in a small bar,the bar number 1;
The steel pipe type:48 dia x 3.5
Cross rod and the vertical rod connecting mode of single fastener;
1.1 erection scheme and procedure
Landing scaffold erection sequence is as follows ( project only to see the 7 layer below the scaffolding and utility )
(1)The ground tamping,pole spacing according to the placement of prefabricated concrete cushion block.
(2)The erection procedures :placed a sweeping rod,by a vertical pole and a sweeping rod fastening,a sweeping rod small lateral pole and pole and a sweeping rod fastening to install first step large bar and rod fastening install first step,second step rail mounted a large bar install the third rail with the temporary braces ( the upper and the first major rail fastening,installing wall connecting rod after the demolition ),installed in third,four large bar and small bar,rod,connecting rod connecting wall with a scissors to spread sheet,rolling scaffold guardrail plate block feet,and set up safety net protection.
(3)The longitudinal ends along the scaffold and scaffolding outside corner,in every 9 M with inclined rod into scissors,top-down sequential setting,slant rod and ground into 45-60 degree angle,scissors pipe joint application of lap,lap length of not less than 40CM.
(4)The scaffolding outside since second steps,each step of 1.2M high protective railing and 30CM high block feet.
(5)The erection with a rod with correction of the vertical and horizontal deviation,while moderate tightening fastening,connecting rod fastener openings shall be toward the shelf,medial,bolt face,preventing entry of rain water.
(6)As the rod intersect protruding end is greater than 100MM,preventing rod slip.
(7)Scissors,erected to a slant buckle on the vertical rod,the other end button on a small rail extension,oblique rod fastener and the upright rod distance not greater than 200MM.
The inner frame distance from the wall length 0.15m;
A large bar on lap in a small bar,the bar number 1;
The steel pipe type:48 dia x 3.5
Cross rod and the vertical rod connecting mode of single fastener;
1.1 erection scheme and procedure
Landing scaffold erection sequence is as follows ( project only to see the 7 layer below the scaffolding and utility )
(1)The ground tamping,pole spacing according to the placement of prefabricated concrete cushion block.
(2)The erection procedures :placed a sweeping rod,by a vertical pole and a sweeping rod fastening,a sweeping rod small lateral pole and pole and a sweeping rod fastening to install first step large bar and rod fastening install first step,second step rail mounted a large bar install the third rail with the temporary braces ( the upper and the first major rail fastening,installing wall connecting rod after the demolition ),installed in third,four large bar and small bar,rod,connecting rod connecting wall with a scissors to spread sheet,rolling scaffold guardrail plate block feet,and set up safety net protection.
(3)The longitudinal ends along the scaffold and scaffolding outside corner,in every 9 M with inclined rod into scissors,top-down sequential setting,slant rod and ground into 45-60 degree angle,scissors pipe joint application of lap,lap length of not less than 40CM.
(4)The scaffolding outside since second steps,each step of 1.2M high protective railing and 30CM high block feet.
(5)The erection with a rod with correction of the vertical and horizontal deviation,while moderate tightening fastening,connecting rod fastener openings shall be toward the shelf,medial,bolt face,preventing entry of rain water.
(6)As the rod intersect protruding end is greater than 100MM,preventing rod slip.
(7)Scissors,erected to a slant buckle on the vertical rod,the other end button on a small rail extension,oblique rod fastener and the upright rod distance not greater than 200MM.
看了 英语翻译搭设尺寸为:立杆的横...的网友还看了以下:
高一英语翻译1在茶馆中休息片刻。---------------------------atatea 2020-05-13 …
英语翻译1.在写论文之前,我先选好我要翻译的小说.上网查询小说的大概内容和中心思想,然后选择一个章 2020-05-13 …
英语翻译翻译:在光明媚的一天,我么在一起回忆童年不要和用翻译软件翻译来的结果我觉得在阳光明媚的一天 2020-07-06 …
英语翻译尺码说明:1鞋底的尺码有:EUR37--EUR44(EUR46).请根据以下男士皮鞋国际标 2020-07-13 …
英语翻译我在翻译英语的时候,有时候把句子读下来但不知道是什么意思,非得用中文翻译才行,大家是怎么翻译 2020-11-16 …
英语翻译语境是这样的:我在路上,我在你身旁!我的意思是:就只要翻译“我在!”就是一个句子,没有其他! 2020-11-23 …
英语翻译现在各国语言都可以互相翻译,都可以学习到另一种语言.但是在最初的时候,两种语言还不能互相翻译 2020-12-01 …
外贸英语翻译39在这一系列尺码中是小码,43、44才是中码.如果小码的39的胸围做120/116厘米 2020-12-06 …
英语翻译你在CAP中所填写的永久对策:更换rivet的尺寸,以及改善模具尺寸,请明确告知rivet的 2020-12-14 …
英语翻译本人即将毕业,毕业论文需要翻译一篇相关英语文献,即pdf格式文件5页,求英语牛人帮忙翻译.自 2021-01-27 …