(75)are individuals and organizations that are actively involved in the project,or whose i

题目

(75)are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

A.Project manager

B.Project stakeholders

C.Sponsor

D.Project team member

参考答案
正确答案:B