During planning you sit down and estimate the time needed for each task and total them to
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate should be the same as the customer's required completion date
英语,连词成句,快!1,breakfast,he,every,eats,for,them,and, 英语 2020-04-25 …
把下面的单词连接成英语句子together,he,called,them,and,asked,hi 英语 2020-04-27 …
英语翻译HRM is the process for creating and maintaini 英语 2020-05-14 …
in the second place,if new teachers and doctors a 英语 2020-05-14 …
英语翻译The voyage to find the one piece is a long an 英语 2020-05-16 …
Tell them what you're going to tell them,tell the 英语 2020-05-16 …
it is necessary for them to learn the language in 英语 2020-05-16 …
Some of them,and others are young peopleSome of t 英语 2020-05-16 …
people ______ under different star signs have dif 英语 2020-05-16 …
英语,改同义句 1.There's no time for them to chat with y 英语 2020-05-16 …