早教吧作业答案频道 -->英语-->
PMP,TellmetheanswerandwhyYouareworkingonaprojectteamthathasbeenassignedtodeterminetheumberofwhaleskilledbytheinternationalcommercialfishingindustryinthepast2years.Yourcompanyreceivedagrantfor$400,00fromtheU.S.D
题目详情
PMP,Tell me the answer and why
You are working on a project team that has been assigned to determine the umber of whales killed by the international commercial fishing industry in the past 2years.Your company received a grant for$400,00 from the U.S.Department of Commerce for this project.The final report is due in 1 month.You have prepared an algorithm to calculate the total number killed based on a representative sample of beached whales found on Grand Cayman form 1980 to 1999.You were supposed to obtain these data as part of the research project,but your management used $350,000 of the money for other purposes.The deadline is rapidly approaching and your project manager has asked you to complete the project with incomplete data.You have to formally present your results to your CEO next Tuesday.The final report must be submitted to the Commerce Department to receive the monies due.In this situation you should
A.Prepare a rough estimate based on your knowledge of the subject,and complete the project
B.Explain in writing and in your oral presentation that you cannot complete the project because of the incomplete data
C.Use the results of research prepared by another organization as the basis for your effort,even though you do not have access to the raw data
D.Inform management that you need additional time,and ask for a formal extension
You are working on a project team that has been assigned to determine the umber of whales killed by the international commercial fishing industry in the past 2years.Your company received a grant for$400,00 from the U.S.Department of Commerce for this project.The final report is due in 1 month.You have prepared an algorithm to calculate the total number killed based on a representative sample of beached whales found on Grand Cayman form 1980 to 1999.You were supposed to obtain these data as part of the research project,but your management used $350,000 of the money for other purposes.The deadline is rapidly approaching and your project manager has asked you to complete the project with incomplete data.You have to formally present your results to your CEO next Tuesday.The final report must be submitted to the Commerce Department to receive the monies due.In this situation you should
A.Prepare a rough estimate based on your knowledge of the subject,and complete the project
B.Explain in writing and in your oral presentation that you cannot complete the project because of the incomplete data
C.Use the results of research prepared by another organization as the basis for your effort,even though you do not have access to the raw data
D.Inform management that you need additional time,and ask for a formal extension
▼优质解答
答案和解析
B.Explain in writing and in your oral presentation that you cannot complete the project because of the incomplete data显然,项目资金严重缺乏,而目前的数据不完整,因此必须提交正式变更申请....
看了PMP,Tellmethean...的网友还看了以下:
英语翻译由于level不够的原因年初没有在GEMS系统里做设定目标,所以现在提交不了,只是在线下做 2020-05-13 …
P,MP,PMP,MPMP,PMPMP分别代表什么意思聪明的你一定会知道的对不对? 2020-07-20 …
PMP项目章程在收尾工作时的用处?以下哪项描述了在工作完成时,项目章程被用来:A.确保所有的团队成 2020-07-20 …
PMP考试题求助一个项目有下列风险:5%的概率需要增加接受测试,造成3个星期的延误;50%的概率下软 2020-11-03 …
PMP测试题某个新产品研发项目,预计投资200万美元.该产品未来市场前景很好的概率为50%,可收入1 2020-12-04 …
承认书checklist里的PMP是什么意思? 2020-12-10 …
今年两会上PMp.少成为热点名词,PMp.少是指大气中直径小于或等于p.少微米的颗粒物,可被吸入肺部 2021-01-01 …
P————————————————屁MP———————————————马屁PMP—————————— 2021-01-01 …
PMP,TellmetheanswerandwhyYouroldestdaughterrecentl 2021-01-01 …
PMP,TellmetheanswerandwhyYouareworkingonaprojectte 2021-01-01 …